New Stillwater bridge opening day delayed to 2017

The bridge project has suffered several setbacks that prompted the revised completion target, related roadwork remains on track for timely completion.

By St. Croix 360 | January 8, 2016 | 2 minute read

  • Facebook
  • Twitter
  • Email
  • Print
  • More
  • LinkedIn
  • Tumblr
  • Pocket
  • Telegram

Via the St. Croix Crossing project website:

December 2015, photo via St. Croix Crossing project.

December 2015, photo via St. Croix Crossing project.

The Minnesota and Wisconsin Departments of Transportation this week announced that the St. Croix River Crossing project will be open to traffic by the fall of 2017. In September, MnDOT and WisDOT and the contractor for the project, Lunda/Ames Joint Venture, announced that the original completion date in 2016 was not attainable, and that a new completion date would be set by the end of 2015. The date was determined by analyzing work done to date, and work that remains.

“We believe this new date is well within the project team’s capability to meet,” said Michael Beer, MnDOT’s project director. “It is a large and complex project, and we want to be sure that it is done safely and meets our high standards for quality.”

MnDOT and WisDOT are committed to working with the Lunda/Ames Joint Venture to complete the St. Croix River Crossing project in the most efficient and cost-effective manner possible. The agencies at this time are not considering legal action against the contractor. At this point, working with the joint venture to resolve the schedule issue will save taxpayer money and reduce total project construction time.

The roadway portions of the project remain on track. Improvements to Highway 36 in Minnesota and Highway 64 in Wisconsin, which will connect to the bridge, are either complete or on-schedule.

About the Bridge Project Delays

Throughout the construction process, the St. Croix River Crossing project has faced a variety of challenges. More details are below.

  • Workforce Shortage – The strengthening regional economy has made it challenging for the contractor to find enough skilled and experienced workers for the project.
  • Equipment Issues – During the 2015 construction season, the segment shuttle crane at Grey Cloud casting yard broke down several times, delaying the movement of segments onto the barges. Each breakdown caused delays lasting from one day to one week. In July, the segment lifter broke down on Pier 9, so segments couldn’t be erected. This caused an additional week-long delay. Much of this specialized equipment is unique to this project.
  • Project Complexity – The 3,200 foot span crosses over the federally protected St. Croix River. The complexity and length of the bridge has slowed progress.
  • Material Shortages – Acquiring the necessary concrete forms to make the segments for the bridge was delayed five months in 2014. Only two American companies make these forms, and the selected company’s owner died and the company subsequently lost its lead engineer. The timing of these events caused the company to delay fabrication of the forms.
  • Weather Delays – Minnesota typically has an eight-month construction season, at the longest. The St. Croix River experienced high water levels in spring 2014, which was a key time in the construction of the bridge piers. The high water caused a two-week delay. Progress was further slowed in 2014 when winter arrived early. This year’s relatively mild winter has helped improve the schedule.

Related articles:

Follow

  • Email
  • Facebook
  • RSS
  • Twitter

Features

Two inches and 6,000 gallons: A swollen century on the St. Croix River

Cold comfort

New preserve will let students, community, and anglers experience the Kinnickinnic River

St. Croix 360 is now 100% supported by readers.

Click here to contribute →

 

Latest News

Stillwater restaurant’s trees spared as construction starts on new walkway

Interstate Park and Ice Age Trail prove popular during pandemic

River Falls reservoir drawn down for good after dam damaged by flood

City on lower St. Croix considers housing ordinance in conflict with river rules

St. Croix forestry conference will connect people working for watershed woods

Privacy & Cookies: This site uses cookies. By continuing to use this website, you agree to their use.
To find out more, including how to control cookies, see here: Cookie Policy

About

St. Croix 360 builds support for river stewardship, and connects people and organizations. It is an independent news source produced by Greg Seitz, with past support from the St. Croix River Association.

Donate to St. Croix 360 today »

Story of 360

One of the biggest challenges facing the St. Croix River is harmful blooms of algae in in the lower river, due to excess nutrients in runoff. The goal is to restore the river by reducing phosphorus levels to 360 tons/year. Learn more »

Share Your News

St. Croix 360 is powered by a broad community of St. Croix River-loving people. Please visit our submission page to send tips, press releases, and other news.

Submit an Event

Lower St. Croix: St. Croix 360 partners with online calendar St. Croix Splash.

  • Submit your events to Splash.
  • Share it with St. Croix 360 for promotion.

For events elsewhere in the watershed, contact St. Croix 360 directly.

St. Croix 360 Syndication

To help increase awareness of the St. Croix River, news organizations and other outlets are free to share St. Croix 360 content, as long as you follow a few simple rules.

Republish St. Croix 360 stories »

Partners

  • St. Croix River Association
  • St. Croix Watershed Research Station
  • ArtReach St. Croix
  • You and all St. Croix 360's readers!
Handcrafted in May Township, Minnesota. Please contribute today »
loading Cancel
Post was not sent - check your email addresses!
Email check failed, please try again
Sorry, your blog cannot share posts by email.